Downtown BRT route over-budget as remaining routes face double-digit inflation
Inflation has driven the cost to build London’s first rapid transit route over budget and threatens to increase the price tag for the two remaining routes.
A new report to the Civic Works Committee (CWC) reveals building the $23.3 million Downtown Loop cost 1.7 per cent ($331,000) more than budgeted.
Cost overruns must be covered by the city.
“So far we’ve been really successful in limiting our budget exceedance to a small amount,” explains director of construction and infrastructure Jennie Dann. “But we know that the factors that are impacting the cost of these projects are not going away anytime soon.”
The report warns inflationary pressures are also anticipated to impact the more expensive East London Link and Wellington Gateway routes.
The budget approved five years ago did not anticipate construction costs to rise so quickly.
“Recent construction price escalations have been observed following approval of the EA (Shift BRT Environmental Assessment) cost estimates from 2018,” reads the CWC report.
Specifically, the 2018 Environmental Assessment estimated annual inflation at 2 per cent to 3 per cent, but Statistics Canada’s Construction Price Index is currently at 12.5 per cent.
In 2018, Dann responded to concerns raised by former mayoral candidate Paul Paolatto that the construction budget was overly optimistic:
At the time she wrote to CTV News, “to guard against cost overruns on this project, we have factored in a significant 50 per cent contingency fund— meaning we have done our financial planning in a way that ensures there are no surprises for Londoners.”
Dann now says a surge in construction costs of more than 30 per cent since 2018 couldn’t be anticipated.
“We made reasonable assumptions at the time, and so now we’re at a point where we’re trying to look at whatever options we can to refine our design and work with those pressures to find savings,” she says.
Cost pressures are impacting infrastructure projects across the city.
The cost to build the Adelaide Rail Underpass recently grew from $58 million to $88 million.
Earlier this week, city council supported a $10.2 million dollar adjustment to the city’s Capital Budget related to 18 smaller road projects.
Dann says the city continues to seek cost efficiencies as designs are finalized on the East London Link and Wellington Gateway.
The report also advises that additional funding might be sought in the 2024-27 multi-year budget this December.
“It’s really too early to tell,” adds Dann. “The team is using all of those same really great practices around value engineering and trying to find ways to tighten up the design for the cost savings.”
CTVNews.ca Top Stories
Asking rent prices up 9.3% across Canada, Ontario sees only decline: report
A new report says the average asking rent for a home in Canada in April was up 9.3 per cent compared with a year ago, while a slight month-over-month increase was also recorded for the first time since January.
What is basic income, and how would it impact me?
Parliamentarians are considering a pair of bills aiming to lift people out of poverty through a basic income program, but some fear these types of systems could result in more taxes for Canadians who are already financially struggling.
'I may have some nightmares:' Man survives being bitten by 2 sharks in Bahamas
A man who was bitten by two sharks in the Bahamas said Thursday he's 'thankful that I'm here' while sharing his story of survival.
Magnitude 4.2 earthquake reported off Vancouver Island's west coast
A 4.2-magnitude earthquake was recorded west of Vancouver Island early Friday morning.
Mexico's president accuses press and volunteer searchers for missing people of 'necrophilia'
The administration of Mexico's president has accused the press and volunteer searchers who look for the bodies of missing people of 'necrophilia,' comments that drew criticism this week.
WATCH Expecting an interest rate cut in June? Don't bet on it after new jobs data
Canada's labour market rebounded in April, adding more than 90,000 jobs, a staggering number of new positions after four consecutive months of little change.
Out-of-control wildfire burning near Fort McMurray
As of 9 a.m. on Friday, the wildfire burning 28 kilometres southwest of the northeastern Alberta city was 25 hectares in size.
Prince William says wife Kate is 'doing well'
Prince William said on Friday his wife Kate was 'doing well' in a rare public comment about the Princess of Wales as she undergoes preventative chemotherapy for cancer.
'Irate male' assaulted Newfoundland officers with block of cheese, police say
Police in Newfoundland say patrol officers were assaulted Thursday by a "very irate male" wielding a block of cheese.