That’s a lot of bus fares: London Transit facility for electric fleet pegged at $333 million
The city’s plan to build a new London Transit facility to charge and maintain electric buses has a staggering new price tag: one-third of a billion dollars.
Almost three years after then-mayor Ed Holder charted a course to electrify London’s bus fleet, details about the largest component of that plan are coming into focus in a new report.
A new headquarters and electric bus charging/maintenance facility on London Transit’s Highbury Avenue property will require multiple phases of demolition and construction to ensure bus service is not interrupted.
The report to city council’s Strategic Priorities and Policy (SP&P) Committee estimates it will cost $332.5 million.
“To demolish and rebuild is about $292 million, the remainder of that cost getting us to $332 million deals with the design, the consulting that’s associated, and operational requirements,” explained Kelly Paleczny, general manager of London Transit.
Construction will be divided into two separate projects, the first starting in 2025 and lasting two-and-a-half to three years.
Paleczny explained that London Transit’s current facility is in poor condition and an electric bus fleet will require space and specialized equipment for maintenance and charging.
“Right now this facility maxes out at about 185 buses,” she said. “The new facility on the same site will be 250, so it gives us room to expand.”
In March 2019, city council settled the rapid transit debate by advancing only three of the five routes for senior government funding.
About $119 million originally sought for the north and west routes remains unallocated.
Earlier this year, the federal government shortened the timeline for cities to choose projects for funding through its Investing in Canada Infrastructure Program (ICIP).
The ICIP transit fund is a cost sharing agreement between three levels of government:
- 40 per cent federal government
- 33 per cent provincial government
- 27 per cent municipal government
City staff recommend redirecting the remaining ICIP funding to cover much of the $199.5 million cost of the first project (moving London Transit HQ and building a partial electric bus barn).
Funding sources for the second project ($133 million), to complete the remainder of the specialized electric bus barn, will be determined through future municipal budgets and federal funding programs.
The SP&P Committee will consider directing London’s remaining ICIP funding to the new London Transit facility on Dec. 6.
CTVNews.ca Top Stories
Canada tracked suspected Chinese spy balloon over Canadian airspace since last weekend: sources
The suspected Chinese surveillance balloon that was found floating over sensitive military sites in the western United States had been tracked by Canada's government since last weekend as it passed through Canadian airspace, sources tell CTV News.

Oldest preserved vertebrate brain found in 319-million-year-old fish fossil
The oldest preserved vertebrate brain has been found in a 319-million-year-old fossilized fish skull that was removed from an English coal mine over a century ago.
B.C. man who was mistaken for target, shot by police in 2013 has lawsuit dismissed
A B.C. man who was mistaken for the target in a police takedown and shot by an officer in 2013 has had his lawsuit alleging negligence dismissed.
Bodies are those of 3 rappers missing nearly 2 weeks: Detroit police
Three bodies found in a vacant Detroit-area apartment building have been identified as those of three aspiring rappers who went missing nearly two weeks ago, police said Friday.
Jury: Musk didn't defraud investors with 2018 Tesla tweets
A jury on Friday decided Elon Musk didn't deceive investors with his 2018 tweets about electric automaker Tesla.
Stars disappearing before our eyes faster than ever: report
A new research from a citizen science program suggests that stars are disappearing before our eyes at an 'astonishing rate.'
Ottawa tight-lipped on details as Canada, U.S. call out China over balloon
Canada announced that it had called China's ambassador onto the carpet as Ottawa and Washington expressed their disapproval Friday over a high-altitude balloon found to have been hovering over sensitive sites in the United States.
Federal department fires 49 employees for claiming CERB while employed
A federal government department has fired 49 employees who received the Canada Emergency Response Benefit while they were employed.
White-tailed deer harbouring COVID-19 variants thought to be nearly extinct in humans: study
White-tailed deer may be a reservoir for COVID-19 variants of concern including Alpha, Delta and Gamma, according to new research out of Cornell University that raises questions about whether deer could re-introduce nearly extinct variants back into the human population.