That’s a lot of bus fares: London Transit facility for electric fleet pegged at $333 million
The city’s plan to build a new London Transit facility to charge and maintain electric buses has a staggering new price tag: one-third of a billion dollars.
Almost three years after then-mayor Ed Holder charted a course to electrify London’s bus fleet, details about the largest component of that plan are coming into focus in a new report.
A new headquarters and electric bus charging/maintenance facility on London Transit’s Highbury Avenue property will require multiple phases of demolition and construction to ensure bus service is not interrupted.
The report to city council’s Strategic Priorities and Policy (SP&P) Committee estimates it will cost $332.5 million.
“To demolish and rebuild is about $292 million, the remainder of that cost getting us to $332 million deals with the design, the consulting that’s associated, and operational requirements,” explained Kelly Paleczny, general manager of London Transit.
Construction will be divided into two separate projects, the first starting in 2025 and lasting two-and-a-half to three years.
Paleczny explained that London Transit’s current facility is in poor condition and an electric bus fleet will require space and specialized equipment for maintenance and charging.
“Right now this facility maxes out at about 185 buses,” she said. “The new facility on the same site will be 250, so it gives us room to expand.”
In March 2019, city council settled the rapid transit debate by advancing only three of the five routes for senior government funding.
About $119 million originally sought for the north and west routes remains unallocated.
Earlier this year, the federal government shortened the timeline for cities to choose projects for funding through its Investing in Canada Infrastructure Program (ICIP).
The ICIP transit fund is a cost sharing agreement between three levels of government:
- 40 per cent federal government
- 33 per cent provincial government
- 27 per cent municipal government
City staff recommend redirecting the remaining ICIP funding to cover much of the $199.5 million cost of the first project (moving London Transit HQ and building a partial electric bus barn).
Funding sources for the second project ($133 million), to complete the remainder of the specialized electric bus barn, will be determined through future municipal budgets and federal funding programs.
The SP&P Committee will consider directing London’s remaining ICIP funding to the new London Transit facility on Dec. 6.
CTVNews.ca Top Stories
B.C. tenants evicted for landlord's use after refusing large rent increase to take over neighbouring suite
Ashley Dickey and her mother rented part of the same Coquitlam duplex in three different decades under three different landlords.
Mountain guide dies after falling into a crevasse in Banff National Park
A man who fell into a crevasse while leading a backcountry ski group deep in the Canadian Rockies has died.
Expert warns of food consumption habits amid rising prices
A new survey by Dalhousie University's Agri-Food Analytics Lab asked Canadians about their food consumption habits amid rising prices.
MPP Sarah Jama asked to leave Ontario legislature for wearing keffiyeh
MPP Sarah Jama was asked to leave the Legislative Assembly of Ontario by House Speaker Ted Arnott on Thursday for wearing a keffiyeh, a garment which has been banned at Queen’s Park.
Charlie Woods, son of Tiger, shoots 81 in U.S. Open qualifier
Charlie Woods failed to advance in a U.S. Open local qualifying event Thursday, shooting a 9-over 81 at Legacy Golf & Tennis Club.
Ex-tabloid publisher testifies he scooped up possibly damaging tales to shield his old friend Trump
As Donald Trump was running for president in 2016, his old friend at the National Enquirer was scooping up potentially damaging stories about the candidate and paying out tens of thousands of dollars to keep them from the public eye.
Here's why provinces aren't following Saskatchewan's lead on the carbon tax home heating fight
After Prime Minister Justin Trudeau said the federal government would still send Canada Carbon Rebate cheques to Saskatchewan residents, despite Saskatchewan Premier Scott Moe's decision to stop collecting the carbon tax on natural gas or home heating, questions were raised about whether other provinces would follow suit. CTV News reached out across the country and here's what we found out.
Montreal actress calls Weinstein ruling 'discouraging' but not surprising
A Montreal actress, who has previously detailed incidents she had with disgraced Hollywood producer Harvey Weinstein, says a New York Court of Appeals decision overturning his 2020 rape conviction is 'discouraging' but not surprising.
Caleb Williams, Jayden Daniels and Drake Maye make it four NFL drafts with quarterbacks going 1-3
Caleb Williams is heading to the Windy City, aiming to become the franchise quarterback Chicago has sought for decades.