Downtown BRT route over-budget as remaining routes face double-digit inflation
Inflation has driven the cost to build London’s first rapid transit route over budget and threatens to increase the price tag for the two remaining routes.
A new report to the Civic Works Committee (CWC) reveals building the $23.3 million Downtown Loop cost 1.7 per cent ($331,000) more than budgeted.
Cost overruns must be covered by the city.
“So far we’ve been really successful in limiting our budget exceedance to a small amount,” explains director of construction and infrastructure Jennie Dann. “But we know that the factors that are impacting the cost of these projects are not going away anytime soon.”
The report warns inflationary pressures are also anticipated to impact the more expensive East London Link and Wellington Gateway routes.
The budget approved five years ago did not anticipate construction costs to rise so quickly.
“Recent construction price escalations have been observed following approval of the EA (Shift BRT Environmental Assessment) cost estimates from 2018,” reads the CWC report.
Specifically, the 2018 Environmental Assessment estimated annual inflation at 2 per cent to 3 per cent, but Statistics Canada’s Construction Price Index is currently at 12.5 per cent.
In 2018, Dann responded to concerns raised by former mayoral candidate Paul Paolatto that the construction budget was overly optimistic:
At the time she wrote to CTV News, “to guard against cost overruns on this project, we have factored in a significant 50 per cent contingency fund— meaning we have done our financial planning in a way that ensures there are no surprises for Londoners.”
Dann now says a surge in construction costs of more than 30 per cent since 2018 couldn’t be anticipated.
“We made reasonable assumptions at the time, and so now we’re at a point where we’re trying to look at whatever options we can to refine our design and work with those pressures to find savings,” she says.
Cost pressures are impacting infrastructure projects across the city.
The cost to build the Adelaide Rail Underpass recently grew from $58 million to $88 million.
Earlier this week, city council supported a $10.2 million dollar adjustment to the city’s Capital Budget related to 18 smaller road projects.
Dann says the city continues to seek cost efficiencies as designs are finalized on the East London Link and Wellington Gateway.
The report also advises that additional funding might be sought in the 2024-27 multi-year budget this December.
“It’s really too early to tell,” adds Dann. “The team is using all of those same really great practices around value engineering and trying to find ways to tighten up the design for the cost savings.”
CTVNews.ca Top Stories
Doctors ask Liberal government to reconsider capital gains tax change
The Canadian Medical Association is asking the federal government to reconsider its proposed changes to capital gains taxation, arguing it will affect doctors' retirement savings.
Keeping these exotic pets is 'cruel' and 'dangerous,' Canadian animal advocates say
Canadian pet owners are finding companionship beyond dogs and cats. Tigers, alligators, scorpions and tarantulas are among some of the exotic pets they are keeping in private homes, which pose risks to public safety and animal welfare, advocates say.
Demonstrators kicked out of Ontario legislature for disruption after failed keffiyeh vote
A group of demonstrators were kicked out of the legislature after a second NDP motion calling for unanimous consent to reverse a ban on the keffiyeh failed to pass.
BREAKING Man wanted in connection with deadly shooting in Toronto tops list of most wanted fugitives in Canada
A 35-year-old man wanted in connection with the murder of Toronto resident 29-year-old Sharmar Powell-Flowers nine months ago has topped the list of the BOLO program’s 25 most wanted fugitives across Canada, police announced Tuesday.
Prince William and wife Kate thank public for birthday messages for son Louis
Prince William and his wife Kate thanked the public for their messages which had been sent to mark the sixth birthday of their youngest son Louis on Tuesday.
She was the closest she'd ever been to meeting her biological father. Then life dealt her a blow
Anne Marie Cavner was the closest she'd ever been to meeting her biological father, but then life dealt her a blow. From an unexpected loss to a host of new relationships, a DNA test changed her life, and she doesn't regret a thing.
How quietly promised law changes in the 2024 federal budget could impact your day-to-day life
The 2024 federal budget released last week includes numerous big spending promises that have garnered headlines. But, tucked into the 416-page document are also series of smaller items, such as promising to amend the law regarding infant formula and to force banks to label government rebates, that you may have missed.
Fire engulfs old Edmonton municipal airport hangar
A historical hangar at the former Edmonton municipal airport beside the NAIT main campus was on fire Monday night.
Soft skills, preparation can help new graduates land jobs, experts say
As new graduates enter the workforce over the next few weeks, they are likely to face challenges getting their foot in the door and must be prepared to effectively communicate what they bring to the company.