Downtown BRT route over-budget as remaining routes face double-digit inflation
Inflation has driven the cost to build London’s first rapid transit route over budget and threatens to increase the price tag for the two remaining routes.
A new report to the Civic Works Committee (CWC) reveals building the $23.3 million Downtown Loop cost 1.7 per cent ($331,000) more than budgeted.
Cost overruns must be covered by the city.
“So far we’ve been really successful in limiting our budget exceedance to a small amount,” explains director of construction and infrastructure Jennie Dann. “But we know that the factors that are impacting the cost of these projects are not going away anytime soon.”
The report warns inflationary pressures are also anticipated to impact the more expensive East London Link and Wellington Gateway routes.
The budget approved five years ago did not anticipate construction costs to rise so quickly.
“Recent construction price escalations have been observed following approval of the EA (Shift BRT Environmental Assessment) cost estimates from 2018,” reads the CWC report.
Specifically, the 2018 Environmental Assessment estimated annual inflation at 2 per cent to 3 per cent, but Statistics Canada’s Construction Price Index is currently at 12.5 per cent.
In 2018, Dann responded to concerns raised by former mayoral candidate Paul Paolatto that the construction budget was overly optimistic:
At the time she wrote to CTV News, “to guard against cost overruns on this project, we have factored in a significant 50 per cent contingency fund— meaning we have done our financial planning in a way that ensures there are no surprises for Londoners.”
Dann now says a surge in construction costs of more than 30 per cent since 2018 couldn’t be anticipated.
“We made reasonable assumptions at the time, and so now we’re at a point where we’re trying to look at whatever options we can to refine our design and work with those pressures to find savings,” she says.
Cost pressures are impacting infrastructure projects across the city.
The cost to build the Adelaide Rail Underpass recently grew from $58 million to $88 million.
Earlier this week, city council supported a $10.2 million dollar adjustment to the city’s Capital Budget related to 18 smaller road projects.
Dann says the city continues to seek cost efficiencies as designs are finalized on the East London Link and Wellington Gateway.
The report also advises that additional funding might be sought in the 2024-27 multi-year budget this December.
“It’s really too early to tell,” adds Dann. “The team is using all of those same really great practices around value engineering and trying to find ways to tighten up the design for the cost savings.”
CTVNews.ca Top Stories
Unable to leave Syria, mothers of Canadian children forfeit repatriation to keep their families together
In a choice forced upon them by the Canadian government, four mothers have made the agonizing decision to forfeit an opportunity to repatriate their children from open air prisons in northeast Syria.

MP Han Dong issues libel notice to Global News over China interference reporting
Lawyers representing Toronto MP Han Dong served Global News with a libel notice on Friday over reports that alleged he spoke to a Chinese diplomat in February 2021 about delaying the release of the two Michaels, and that he was a 'witting affiliate' of Chinese interference networks – allegations that Dong denies.
Federal minimum wage, taxes on alcohol: Here's what's changing in Canada April 1
The federal minimum wage is increasing from $15.55 per hour to $16.65, and taxes are going up on gas and alcohol nationwide starting April 1.
Here's what to expect from the Canadian cottage market this year
A recent report from Royal LePage is predicting a drop in prices for Canadian cabins and cottages this year as demand softens from economic uncertainty and low housing stock.
Interim RCMP commissioner would support Criminal Code changes for stricter gun laws
Interim RCMP commissioner Michael Duheme says he would support the Criminal Code changes recommended in the Mass Casualty Commission report to implement stricter gun laws.
Akwesasne: Bodies of two more migrants found, bring total dead to eight
Police say the bodies of eight migrants have been retrieved from the waters off the Mohawk Territory of Akwesasne, straddling the Canada - U.S. border. The people whose bodies were recovered Thursday and Friday consisted of two families of Romanian and Indian origins who were likely trying to enter the U.S. illegally, police said Friday.
Donald Trump facing at least one felony charge in New York case: AP sources
Former U.S. president Donald Trump is facing multiple charges of falsifying business records, including at least one felony offence, in the indictment handed down by a Manhattan grand jury, two people familiar with the matter told The Associated Press on Friday.
A 106-year-old from the Philippines is Vogue's oldest ever cover model
Vogue Philippines has revealed Apo Whang-Od as the cover star of its April issue, a move that makes the 106-year-old tattoo artist from the Philippines the oldest person ever to appear on the front of Vogue.
Trudeau defends appointment of cabinet minister's sister-in-law as interim ethics commissioner
Prime Minister Justin Trudeau is defending the appointment of senior Liberal cabinet minister Dominic LeBlanc's sister-in-law as Canada's interim ethics commissioner.