Downtown BRT route over-budget as remaining routes face double-digit inflation
Inflation has driven the cost to build London’s first rapid transit route over budget and threatens to increase the price tag for the two remaining routes.
A new report to the Civic Works Committee (CWC) reveals building the $23.3 million Downtown Loop cost 1.7 per cent ($331,000) more than budgeted.
Cost overruns must be covered by the city.
“So far we’ve been really successful in limiting our budget exceedance to a small amount,” explains director of construction and infrastructure Jennie Dann. “But we know that the factors that are impacting the cost of these projects are not going away anytime soon.”
The report warns inflationary pressures are also anticipated to impact the more expensive East London Link and Wellington Gateway routes.
The budget approved five years ago did not anticipate construction costs to rise so quickly.
“Recent construction price escalations have been observed following approval of the EA (Shift BRT Environmental Assessment) cost estimates from 2018,” reads the CWC report.
Specifically, the 2018 Environmental Assessment estimated annual inflation at 2 per cent to 3 per cent, but Statistics Canada’s Construction Price Index is currently at 12.5 per cent.
In 2018, Dann responded to concerns raised by former mayoral candidate Paul Paolatto that the construction budget was overly optimistic:
At the time she wrote to CTV News, “to guard against cost overruns on this project, we have factored in a significant 50 per cent contingency fund— meaning we have done our financial planning in a way that ensures there are no surprises for Londoners.”
Dann now says a surge in construction costs of more than 30 per cent since 2018 couldn’t be anticipated.
“We made reasonable assumptions at the time, and so now we’re at a point where we’re trying to look at whatever options we can to refine our design and work with those pressures to find savings,” she says.
Cost pressures are impacting infrastructure projects across the city.
The cost to build the Adelaide Rail Underpass recently grew from $58 million to $88 million.
Earlier this week, city council supported a $10.2 million dollar adjustment to the city’s Capital Budget related to 18 smaller road projects.
Dann says the city continues to seek cost efficiencies as designs are finalized on the East London Link and Wellington Gateway.
The report also advises that additional funding might be sought in the 2024-27 multi-year budget this December.
“It’s really too early to tell,” adds Dann. “The team is using all of those same really great practices around value engineering and trying to find ways to tighten up the design for the cost savings.”
CTVNews.ca Top Stories
Liberals to go after predatory lending in today's budget, invest in dental care plan
Finance Minister Chrystia Freeland is set to table a federal budget in the House of Commons on Tuesday afternoon, which a federal source says will include plans to go after predatory lending and more details on dental care as part of a pitch to make life more affordable.

Nearly all Canadian adults had COVID antibodies for about half of 2022, most through previous infection: survey
A newly released survey finds nearly all Canadian adults had antibodies against COVID-19 for about half of 2022, with most acquiring them through a previous infection.
Nashville police release chilling security camera footage of suspected school shooter
Nashville police have released security camera footage of a suspected shooter entering the private Christian elementary school. The shooting claimed the lives of three children, all aged nine, and three adults.
Family sues Hamilton, Ont. school board after 5-year-old girl loses part of finger in alleged bullying incident
The mother of a five-year-old girl said her daughter was allegedly bullied so badly she was left with a partially amputated finger from an incident in the washroom.
Quebec police officer stabbed and killed during arrest, second wounded
A Quebec provincial police officer was fatally stabbed Monday night while performing an arrest in Louiseville, west of Trois-Rivieres, Que. The Surete du Quebec (SQ) has confirmed the identity of the officer, Sgt. Maureen Breau, who had been on the force for over 20 years. She was assigned to the post of the MRC de Maskinonge. Another officer was injured during the incident, but their life is not in danger.
Nashville shooter was ex-student with detailed plan to kill
The former student who shot through the doors of a Christian elementary school in Nashville and killed three children and three adults had drawn a detailed map of the school, including potential entry points, and conducted surveillance of the building before carrying out the massacre.
Russian whose daughter drew anti-war picture gets two years' jail but flees
A Russian who was investigated by police after his daughter drew an anti-war picture at school was sentenced on Tuesday to two years in a penal colony on charges of discrediting the armed forces.
Some Flair customers say they're owed more after plane seizures, flight cancellations
Flair Airlines said Monday it has reimbursed virtually all 1,900 passengers whose flights were cancelled after the seizure of four of the carrier's planes earlier this month, but some customers say they are owed more money.
'It was my responsibility': Manitoba girl saves siblings from destructive house fire
A 12-year-old Manitoba girl is being hailed a hero after saving her two younger brothers from a house fire.